3 Waters

Kaitāia Water Project

Stellar Projects   Kaitāia Water Project
Location Kaitāia, Far North
Timeline Sep 2020 – Aug 2023
Client Far North District Council (FNDC)

Services Provided – Project management services (end-to-end delivery)
– Contract administration and commercial management
– Construction monitoring and site oversight
– Programme and progress management
– Cost tracking and budget control
– Coordination of design consultants
– Resource consent compliance management
– Stakeholder and landowner engagement
– Reporting and performance monitoring

Securing Water Resilience: Delivering Large-Scale Pipeline Infrastructure for Kaitāia

Boosting Kaitāia’s water resilience and reducing reliance on the Awanui River has long been a priority for Far North District Council. The Kaitāia Water Project delivered a step change in supply security.

Stellar Projects provided full project management services for the design and construction of a 14km water transfer pipeline, linking production bores at Sweetwater to the Kaitāia Water Treatment Plant.

Our role covered contract administration, construction monitoring, coordination of design consultants, cost tracking, programme management, and progress reporting. We also managed resource consent compliance and stakeholder engagement, including coordination with landowners along the pipeline route.

The project was delivered on programme and under budget, strengthening the town’s potable water supply, supporting regional workforce capability, and contributing to economic recovery.

Highlights

We are extremely proud of the delivery team’s achievements, including commissioning two production water bores and completing a 14km pipeline, 90% of which needed horizontal drilling. The team also successfully completed two river crossings with engineered brackets and new wingwalls, along with a 38-metre triangular truss bridge for the Bonnetts Road pipeline.

Delivering Complex Infrastructure with Confidence